Pellet Plant Implementation Timeline


Days

1.0 TPH

2.0 TPH

3.0 TPH

4.0 TPH

8.0 TPH

12.0 TPH

+20 Days

Site Visit (if needed)

Site Visit (if needed)

Site Visit (if needed)

Site Visit (if needed)

Site Visit (if needed)

Site Visit (if needed)

+30 Days

Layout Drawing

Layout Drawing

Layout Drawing

Layout Drawing

Layout Drawing

Layout Drawing

+30 Days

Start Site Preparation

Start Site Preparation

Start Site Preparation

Start Site Preparation

Start Site Preparation

Start Site Preparation

+40 Days

Electrical Connection Data

Electrical Connection Data

Electrical Connection Data

Electrical Connection Data

Electrical Connection Data

Electrical Connection Data

+60 Days

Site Ready

Site Ready

Site Ready

Site Ready

Site Ready

Site Ready

+70 Days

Erection Supervision

Erection Supervision

Erection Supervision

Erection Supervision

Erection Supervision

Erection Supervision

+120 Days

Dry Testing & Training

Dry Testing & Training

-

-

-

-

+130 Days

Commissioning

-

Dry Testing & Training

-

-

-

+140 Days

Handover

Commissioning

Commissioning

Dry Testing& Training

-

-

+150 Days

-

Handover

Handover

Commissioning

Dry Testing & Training

Dry Testing & Training

+160 Days

-

-

-

Handover

Commissioning

Commissioning

+165 Days

-

-

-


Handover


+220 Days

-

-

-

-

-

Handover


Note: The timeline provided is a standard practice for handling pellet plant projects. Please request a precise timeline after placing the order, as it may vary due to factors such as unforeseen delays, regulatory requirements, or force majeure conditions.