Pellet Plant Capacity: 1.0 Tonnes Per Hour (TPH)

Summary: Detailed timeline for implementing a 1.0 TPH capacity pellet plant, from order placement to operational handover by SERVODAY.

Days

Milestone

+20 Days

SERVODAY project development team may visit your site, if initial site data is insufficient to approve the location.

+30 Days

SERVODAY provides a layout drawing for your site, showing the placement of plant and machinery, and storage areas.

+30 Days

Start preparing the site from land development to construction as per the confirmed layout.

+40 Days

SERVODAY provides data for electrical connection requirements with loads for the plant.

+94 Days

Site must be ready to receive plant and machinery from SERVODAY.

+95 Days

SERVODAY starts dispatching the plant and machinery.

+105 Days

SERVODAY supervises the erection of the plant at the installation site.

+120 Days

SERVODAY starts dry testing of plant and machinery, including training of your plant operating staff.

+130 Days

SERVODAY commissions the plant.

+140 Days

Plant is handed over to your staff for day-to-day operations.


Pellet Plant Capacity: 2.0 Tonnes Per Hour (TPH)

Summary: Detailed timeline for implementing a 2.0 TPH capacity pellet plant, from order placement to operational handover by SERVODAY.

Days

Milestone

+20 Days

SERVODAY project development team may visit your site, if initial site data is insufficient to approve the location.

+30 Days

SERVODAY provides a layout drawing for your site, showing the placement of plant and machinery, and storage areas.

+30 Days

Start preparing the site from land development to construction as per the confirmed layout.

+40 Days

SERVODAY provides data for electrical connection requirements with loads for the plant.

+104 Days

Site must be ready to receive plant and machinery from SERVODAY.

+105 Days

SERVODAY starts dispatching the plant and machinery.

+115 Days

SERVODAY supervises the erection of the plant at the installation site.

+130 Days

SERVODAY starts dry testing of plant and machinery, including training of your plant operating staff.

+140 Days

SERVODAY commissions the plant.

+150 Days

Plant is handed over to your staff for day-to-day operations.


Pellet Plant Capacity: 3.0 Tonnes Per Hour (TPH)

Summary: Detailed timeline for implementing a 3.0 TPH capacity pellet plant, from order placement to operational handover by SERVODAY.

Days

Milestone

+20 Days

SERVODAY project development team may visit your site, if initial site data is insufficient to approve the location.

+30 Days

SERVODAY provides a layout drawing for your site, showing the placement of plant and machinery, and storage areas.

+30 Days

Start preparing the site from land development to construction as per the confirmed layout.

+40 Days

SERVODAY provides data for electrical connection requirements with loads for the plant.

+109 Days

Site must be ready to receive plant and machinery from SERVODAY.

+110 Days

SERVODAY starts dispatching the plant and machinery.

+125 Days

SERVODAY supervises the erection of the plant at the installation site.

+140 Days

SERVODAY starts dry testing of plant and machinery, including training of your plant operating staff.

+150 Days

SERVODAY commissions the plant.

+160 Days

Plant is handed over to your staff for day-to-day operations.


Pellet Plant Capacity: 4.0 Tonnes Per Hour (TPH)

Summary: Detailed timeline for implementing a 4.0 TPH capacity pellet plant, from order placement to operational handover by SERVODAY.

Days

Milestone

+20 Days

SERVODAY project development team may visit your site, if initial site data is insufficient to approve the location.

+30 Days

SERVODAY provides a layout drawing for your site, showing the placement of plant and machinery, and storage areas.

+30 Days

Start preparing the site from land development to construction as per the confirmed layout.

+40 Days

SERVODAY provides data for electrical connection requirements with loads for the plant.

+119 Days

Site must be ready to receive plant and machinery from SERVODAY.

+120 Days

SERVODAY starts dispatching the plant and machinery.

+135 Days

SERVODAY supervises the erection of the plant at the installation site.

+150 Days

SERVODAY starts dry testing of plant and machinery, including training of your plant operating staff.

+160 Days

SERVODAY commissions the plant.

+170 Days

Plant is handed over to your staff for day-to-day operations.


Capacity-wise Timeline Table for Immediate Reference

Timeline (Days)

1.0 TPH Plant

2.0 TPH Plant

3.0 TPH Plant

4.0 TPH Plant

Initial Site Visit

20

20

20

20

Layout Drawing

30

30

30

30

Site Preparation Start

30

30

30

30

Electrical Data

40

40

40

40

Site Ready for Equipment

94

104

109

119

Equipment Dispatch

95

105

110

120

Supervised Erection

105

115

125

135

Dry Testing & Training

120

130

140

150

Plant Commissioning

130

140

150

160

Handover to Client

140

150

160

170

This timeline is a standard practice for handling the project. Please request a precise timeline after placing the order, as it may vary due to various factors such as COVID-19 and other force majeure conditions.